Coral Harbour Nassau, Bahamas
August - November 2017
Client: Van Oord Dredging and marine Contractors BV
Project:
- Designing and calculating temporary scaffolding and capacity of temporary piles.
- Realisation of foundation for a 150-tonne travel lift.
Techniques used:
- Piling of precast concrete piles (40 pieces, 45 x 45 cm, 14 m' length)
- Installation and removal of steel tubular piles and beams (temporary scaffolding)
Two staff members of Vanthek Projects were on location for the duration of the project.