Idoho, Nigeria
Installing (Part 1): December - March 2018
Removal (Part 2): May - July 2018
Client: Van Oord Dredging and Marine Contractors BV
Project: Supply, construction and removal of complete cofferdam with embossing and anchoring for the purpose of installation HDPE pipelines.
Techniques used:
Features:
Two teams consisting of Piling workers, operators, mechanics and welders, along with all the necessary equipment for the construction of the sheet pile travelled to Nigeria for this project.