Afungi, Mozambique
Project in collaboration with Alphahek
December 2019 - March 2021
Project:
- Cellular Cofferdam Construction for a Temporary Beach Landing at Afungi, Mozambique
Techniques used:
- Vibratory driven piling of in total 16 pieces cellular cells
- Installation of over 1400 pcs of AS500-12 sheet piles
- Cellular guiding frame based on diameter 14,1 m
Features:
- Offshore operations of Marine installation project at the Coast of Mozambique
- In-house engineering and designed hydraulic adjustable Cellular guiding frame